[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151953":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151953,803,2,"多选题","下列关于水力发电工程合同商务管理的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分包项目的施工措施计划、开工申报等应通过承包单位向监理申报",true,{"key":16,"text":17,"correct":18},"B","承建单位与分包单位之间的合同纠纷应由监理机构裁定",false,{"key":20,"text":21,"correct":18},"C","监理与设计单位的关系是监理与被监理的关系",{"key":23,"text":24,"correct":18},"D","施工不符合设计要求时，设计单位可直接向承建单位发出指示",{"key":26,"text":27,"correct":14},"E","项目法人不得擅自变更总监理工程师的指令","AE","2020版教材P332 \u002F 2019版教材P331 （2）工程变更可以由业主、监理机构提出，也可以由设计单位或承建单位提出变更要求和建议，报经业主或由业主授权监理机构按工程承建合同文件规定审查和批准。 除非业主授权或工程承建合同文件另有规定，否则监理机构不受理承建单位与分包单位之间的分包合同纠纷。 监理与施工单位是监理与被监理的关系。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]