[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151951":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151951,803,2,"多选题","工程变更根据其性质与对工程项目的影响程度，一般分为（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","重大工程变更",true,{"key":16,"text":17,"correct":14},"B","较大工程变更",{"key":19,"text":20,"correct":14},"C","一般工程变更",{"key":22,"text":23,"correct":24},"D","主要工程变更",false,{"key":26,"text":27,"correct":14},"E","常规工程变更","ABCE","2020版教材P332 \u002F 2019版教材P331 水力发电工程监理合同商务管理的内容,工程变更的分类。工程变更依据其性质与对工程项目的影响程度，分为重大工程变更、较大工程变更、一般工程变更、常规设计变更四类。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]