[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151949":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151949,803,2,"多选题","下列有关水力发电工程分包管理的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","监理机构应对承建单位提出允许分包的工程项目的分包申请予以审查",true,{"key":16,"text":17,"correct":18},"B","分包项目的工程质量检验、工程变更以及合同支付不需通过承建单位向监理机构申报",false,{"key":20,"text":21,"correct":14},"C","分包项目的施工措施计划、开工申报需通过承建单位向监理机构申报",{"key":23,"text":24,"correct":14},"D","除非业主授权或工程承建合同文件另有规定，否则监理机构不受理承建单位与分包单位之间的分包合同纠纷",{"key":26,"text":27,"correct":18},"E","监理机构应及时受理承建单位与分包单位之间的分包合同纠纷，并协助解决","ACD","2020版教材P333 \u002F 2019版教材P332 根据《水电水利工程施工监理规范》DL\u002FT5U1—2012分包管理监理机构必须在业主和工程承建合同文件授权的范围内，对规定允许分包的工程项目和范围，对承建单位按合同文件规定程序与格式要求申报的分包申请，予以审查和作出批准或不批准的决定。分包项目的施工措施计划、开工申报、工程质量检验、工程变更以及合同支付等，通过承建单位向监理机构申报。除非业主授权或工程承建合同文件另有规定，否则监理机构不受理承建单位与分包单位之间的分包合同纠纷。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]