[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151938":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151938,803,2,"多选题","水利工程建设项目施工准备工作阶段监理工作的基本内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","原材料的储存量及供应计划是否满足开工及施工进度的需要",true,{"key":16,"text":17,"correct":14},"B","进场原材料、中间产品和工程设备的质量、规格是否符合施工合同约定",{"key":19,"text":20,"correct":21},"C","审批工程月进度计划",false,{"key":23,"text":24,"correct":14},"D","应参加、主持或与发包人联合主持召开设计交底会议，由设计单位进行设计文件的技术交底。",{"key":26,"text":27,"correct":21},"E","协助发包人编制合同项目的付款计划","ABD","2020版教材P328 \u002F 2019版教材P327 （2）承包人进场施工设备的数量、规格和性能是否符合施工合同约定，进场情况和计划是否满足开工及施工进度的要求。 （3）进场原材料、中间产品和工程设备的质量、规格是否符合施工合同约定，原材料的储存量及供应计划是否满足开工及施工进度的需要。 3.监理机构应参加、主持或与发包人联合主持召开设计交底会议，由设计单位进行设计文件的技术交底。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]