[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151922":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151922,803,2,"多选题","其他直接费包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","特殊地区施工增加费",true,{"key":16,"text":17,"correct":14},"B","其他费用",{"key":19,"text":20,"correct":21},"C","施工机械使用费",false,{"key":23,"text":24,"correct":14},"D","冬雨期施工增加费",{"key":26,"text":27,"correct":14},"E","夜间施工增加费","ABDE","2020版教材P310 \u002F 2019版教材P309 2根据《水利T程设计概（估）算编制规定（工程部分）》（水总[2014]429号）建筑及安装工程费中其他接费的组成。其他直接费包括冬雨期施工增加费、夜间施工增加费、特殊地区施工增加费、临时设施费、安全生产措施费和其他。选项C为基本直接费。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]