[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151921":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151921,803,2,"多选题","基本直接费包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","人工费",true,{"key":16,"text":17,"correct":14},"B","材料费",{"key":19,"text":20,"correct":14},"C","施工机械使用费",{"key":22,"text":23,"correct":24},"D","规费",false,{"key":26,"text":27,"correct":24},"E","企业管理费","ABC","2020版教材P310 \u002F 2019版教材P309 2根据《水利工程设计概（估）算编制规定（工程部分）》（水总[2014]429号）建筑及安装工程费中基本直接费的组成。基本直接费包括人工费、材料费、施X机械使用费。选项DE为间接费",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]