[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151910":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151910,803,2,"多选题","下列关于砌体工程计量与支付的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","砌筑工程的砂浆应另行支付",false,{"key":16,"text":17,"correct":18},"B","砌筑工程的拉结筋不另行支付",true,{"key":20,"text":21,"correct":18},"C","砌筑工程的垫层不另行支付",{"key":23,"text":24,"correct":14},"D","砌筑工程的伸缩缝、沉降缝应另行支付",{"key":26,"text":27,"correct":18},"E","砌体建筑物的基础清理和施工排水等工作所需的费用不另行支付","BCE","2020版教材P322 \u002F 2019版教材P321 详见（2）砌筑工程的砂浆、拉结筋、垫层、排水管、止水设施、伸缩缝、沉降缝及埋 设件等费用，包含在《工程量清单》相应砌筑项目有效工程量的每立方米工程单价中，发包人不另行支付D（3）承包人按合同要求完成砌体建筑物的基础清理和施工排水等工作所需的费用，包含在《工程量清单》相应砌筑项目有效工程量的每立方米工程单价中，发包人不另行支付。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]