[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151908":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151908,803,2,"多选题","下列关于工程进度横道图的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不形象、直观，且难于编制和理解",false,{"key":16,"text":17,"correct":18},"B","不能明确反映出各项工作之间错综复杂的相互关系",true,{"key":20,"text":21,"correct":18},"C","不能明确地反映出影响工期的关键工作和关键线路",{"key":23,"text":24,"correct":18},"D","不能反映出工作所具有的机动时间",{"key":26,"text":27,"correct":18},"E","不能反映工程费用与工期之间的关系","BCDE","2020版教材P299 \u002F 2019版教材P298 进度控制里面横道图的优缺点，横道计划的优点是形象、直观，且易于编制和理解，因而长期以来被广泛应用于建设工程进度控制中。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]