[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151907":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151907,803,2,"多选题","水利水电工程施工进度计划常用的表达方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":14},"B","工程进度曲线",{"key":19,"text":20,"correct":21},"C","施工强度曲线",false,{"key":23,"text":24,"correct":14},"D","形象进度图",{"key":26,"text":27,"correct":14},"E","网络进度计划","ABDE","2020版教材P299 \u002F 2019版教材P298 施工进度计划常用的表达方法包括那些。工程设计和施工阶段常采用的进度计划表达方法包括：横道图、工程进度曲线、施工进度管理控制曲线..、形象进度图、网络进度计划等。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]