[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151906":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151906,803,2,"多选题","在工程进度曲线中，将实际进度与计划进度进行比较，可以获得的信息是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","实际工程进展速度",true,{"key":16,"text":17,"correct":14},"B","进度超前或拖延的时间",{"key":19,"text":20,"correct":14},"C","工程量的完成情况",{"key":22,"text":23,"correct":14},"D","后续工程进度预测",{"key":25,"text":26,"correct":27},"E","各项工作之间的相互搭接关系",false,"ABCD","2020版教材P300 \u002F 2019版教材P299 施工进度计划表达方法中的工程进度曲线。对实际进度与计划进度进行比较，通过比较可以获得如下信息：（1）实际工程进展速度。（2）进度超前或拖延的时间。（3）工程量的完成情况。（4）后续工程进度预测。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]