[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151901":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151901,803,2,"多选题","根据《水电工程验收管理办法》（2015年修订版），水电工程在（ ）时应进行阶段验收。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","截流",true,{"key":16,"text":17,"correct":18},"B","主体工程完工",false,{"key":20,"text":21,"correct":14},"C","下闸蓄水",{"key":23,"text":24,"correct":18},"D","机电安装工程完工",{"key":26,"text":27,"correct":14},"E","机组启动","ACE","2020版教材P291 \u002F 2019版教材P290 水电工程验收包括阶段验收和竣工验收，其中阶段验收包括工程截流验收、工程蓄水验收、水轮发电机组启动验收",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]