[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151900":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151900,803,2,"多选题","水电工程各阶段验收申请应向省级人民政府能源主管部门报送，下列关于抄送单位的说法，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程蓄水验收申请抄送验收主持单位",true,{"key":16,"text":17,"correct":14},"B","机组启动验收申请抄送电网经营管理单位",{"key":19,"text":20,"correct":21},"C","工程截流验收申请抄送验牧主持单位",false,{"key":23,"text":24,"correct":21},"D","工程蓄水验收申请抄送电网经营管理单位",{"key":26,"text":27,"correct":21},"E","机组启动验收申请抄送验收主持单位","AB","2020版教材P292 \u002F 2019版教材P291 工程蓄水验收，项目法人应根据工程进度安排，在计划下闸蓄水前6个月，向工程所在地省级人民政府能源主管部门报送工程蓄水验收申请，并抄送验收主持单位；机组启动验收，项目法人应在第一台水轮发电机组进行机组启动验收前3个月，向工程所在地省级人民政府能源主管部门报送机组启动验收申请，并抄送电网经营管理单位。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]