[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151898":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151898,803,2,"多选题","根据《水电工程验收管理办法》（2015年修订版），以下关于枢纽工程专项验收的说法，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目法人应在枢纽工程专项验收计划前3个月报送枢纽工程专项验收申请",true,{"key":16,"text":17,"correct":14},"B","枢纽工程专项验收可组织专家组进行现场检查和技术预验收",{"key":19,"text":20,"correct":21},"C","验收委员会主任委员应由验收主持单位主要负责同志担任",false,{"key":23,"text":24,"correct":14},"D","枢纽工程专项验收工作完成后，应出具枢纽工程专项验收鉴定书",{"key":26,"text":27,"correct":14},"E","水电工程分期建设的，可根据工程建设进度分期或一次性进行验收","ABDE","2020版教材P293 \u002F 2019版教材P292 详见验收委员会主任委员由省级人民政府能源主管部门担任，也可委任技术主持单位担任。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]