[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151896":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151896,803,2,"多选题","竣工验收申请报告的主要内容包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目基本情况",true,{"key":16,"text":17,"correct":14},"B","工程建设运行情况",{"key":19,"text":20,"correct":14},"C","专项验收计划",{"key":22,"text":23,"correct":24},"D","专项验收完成情况",false,{"key":26,"text":27,"correct":14},"E","竣工验收总体安排","ABCE","2020版教材P294 \u002F 2019版教材P293 验收申请报告应包括项目基本情况、项目建设运行情况、专项验收计划及竣工验收总体安排等内容。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]