[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151888":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151888,803,2,"多选题","分部工程验收的主要工作是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","鉴定工程是否达到设计标准",true,{"key":16,"text":17,"correct":14},"B","按现行国家或行业技术标准，评定工程质量等级",{"key":19,"text":20,"correct":21},"C","提出工程调度运用方案",false,{"key":23,"text":24,"correct":21},"D","分析投资效益",{"key":26,"text":27,"correct":14},"E","对验收遗留问题提出处理意见","ABE","2020版教材P269 \u002F 2019版教材P272 分部工程验收工作包括以下主要内容：1、检查工程是否达到设计标准会合同约定标准的要求；2、评定工程施工质量等级；3、对验收中发现的问题提出处理意见。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]