[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151882":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151882,803,2,"多选题","下列验收属于阶段验收的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","枢纽工程导（截）流验收",true,{"key":16,"text":17,"correct":14},"B","水库下闸蓄水验收",{"key":19,"text":20,"correct":14},"C","引（调）排水工程通水验收",{"key":22,"text":23,"correct":14},"D","水电站（泵站）首（末）台机组启动验收",{"key":25,"text":26,"correct":27},"E","设计单元工程验收",false,"ABCD","2020版教材P273 \u002F 2019版教材P275 阶段验收应包括枢纽工程导（截）流验收、水库下阐蓄水验收、引（调）排水工程通水验收、水电站（泵站）首（末）台机组启动验收、部分工程投入使用验收以及竣工验收主持单位根据工程建设需要增加的其他验收。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]