[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151881":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151881,803,2,"多选题","下列关于阶段验收的说法，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程截流前，应进行截流前（阶段）验收",true,{"key":16,"text":17,"correct":14},"B","水电站每台机组投入运行前，均应进行机组启动验收",{"key":19,"text":20,"correct":21},"C","大型枢纽工程在截流、蓄水等阶段验收前，必须先进行技术性初步验收",false,{"key":23,"text":24,"correct":14},"D","泵站每台机组投入运行前，均应进行机组启动（阶段）验收",{"key":26,"text":27,"correct":21},"E","对于总台数少于3台的泵站，可待全部机组安装完成后，再进行机组启动验收","ABD","2020版教材P273 \u002F 2019版教材P276 枢纽工程导（截）流前，应进行导（截）流验收； 9.大型工程在阶段验收前，验收主持单位根据工程建设需要，可成立专家组先进行技术预验收，技术预验收工作可参照本规程的有关规定进行。 水电站（泵站）每台机组投入运行前，应进行机组启动验收。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]