[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151871":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151871,803,2,"多选题","水利水电工程项目划分应结合（ ）要求进行。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程结构特点",true,{"key":16,"text":17,"correct":18},"B","施工工艺",false,{"key":20,"text":21,"correct":14},"C","施工部署",{"key":23,"text":24,"correct":18},"D","便于资源供应",{"key":26,"text":27,"correct":14},"E","施工合同要求","ACE","2020版教材P250 \u002F 2019版教材P253 详见水利水电工程项目划分应结合工程结构特点、施工部署及施工合同要求进行，划分结果应有利于保证施工质量以及施工质量管理。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]