[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151869":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151869,803,2,"多选题","以下属于重要隐蔽单元工程的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","主要建筑物的地基开挖",true,{"key":16,"text":17,"correct":14},"B","地下洞室开挖",{"key":19,"text":20,"correct":14},"C","地基防渗",{"key":22,"text":23,"correct":14},"D","加固处理和排水工程",{"key":25,"text":26,"correct":27},"E","电站厂房",false,"ABCD","2020版教材P252 \u002F 2019版教材P254 重要隐蔽单元工程，指主要建筑物的地基开挖、地下洞室开挖、地基防渗、加固处理和排水等隐蔽工程中，对工程安全或使用功能有严重影响的单元工程。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]