[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151856":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151856,803,2,"多选题","在（ ）等前期工作中的工程质量由设计单位负责，设计审查单位负审查责任。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","可行性研究",true,{"key":16,"text":17,"correct":14},"B","可行性研究以前阶段的勘测设计",{"key":19,"text":20,"correct":14},"C","可行性研究以前阶段的规划设计",{"key":22,"text":23,"correct":24},"D","初步设计",false,{"key":26,"text":27,"correct":24},"E","初步设计及以前阶段的勘测设计","ABC","2020版教材P243 \u002F 2019版教材P246 根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），除可行性研究及以前阶段的勘测、规划设计等前期工作中的工程质量由设计单位负责，设计审查单位负审查责任。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]