[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151854":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151854,803,2,"多选题","在工程建设期间，施工单位（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对所承包项目的施工质量负责",true,{"key":16,"text":17,"correct":14},"B","在监理单位验收前对施工质量负全部责任",{"key":19,"text":20,"correct":21},"C","在监理单位验收后对施工质量负间接责任",false,{"key":23,"text":24,"correct":14},"D","在监理单位验收后，对其隐瞒或虚假部分负直接责任",{"key":26,"text":27,"correct":21},"E","对安装的设备质量负责","ABD","2020版教材P244 \u002F 2019版教材P247 根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），施工单位得职责。施工单位对所承包项目的施工质量负责，在监理单位验收前对施工质量负全部责任，在监理单位验收后，对其隐瞒或虚假部分负直接责任。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]