[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151849":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151849,803,2,"多选题","涉及工程安全的重大问题的（ ）发生重大变更时，必须由项目法人报原设计审批部门审查批准。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计负责人",false,{"key":16,"text":17,"correct":18},"B","设计原则",true,{"key":20,"text":21,"correct":18},"C","设计标准",{"key":23,"text":24,"correct":18},"D","设计方案",{"key":26,"text":27,"correct":14},"E","设计理念","BCD","2020版教材P245 \u002F 2019版教材P248 工程规模、安全设防标准、枢纽总体布置、主要建筑物形式、施工期度汛标准及其他涉及工程安全的重大问题的设计原则、标准和方案发生重大变更时，必须由项目法人组织设计单位编制相应的设计文件，并由项目法人报原设计审批部门审查批准。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]