[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151834":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151834,803,2,"多选题","施工用电的重大事故隐患包括未按规定实行（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","三相五线制",true,{"key":16,"text":17,"correct":14},"B","三级配电",{"key":19,"text":20,"correct":14},"C","两级保护",{"key":22,"text":23,"correct":24},"D","内外电分开",false,{"key":26,"text":27,"correct":24},"E","高低压分开","ABC","2020版教材P221 \u002F 2019版教材P224 表1F420051-1中，SJ-Z002，未按规定实行三相五线制或三级配电或两级保护。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]