[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151792":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151792,803,2,"多选题","下列有关质量缺陷的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","水利工程应当实行质量缺陷备案制度",true,{"key":16,"text":17,"correct":18},"B","质量缺陷备案表由项目法人组级填写",false,{"key":20,"text":21,"correct":14},"C","参建单位（人员）必须在质量缺陷备案表上签字",{"key":23,"text":24,"correct":14},"D","质量缺陷备案资料必须按竣工验收的标准制备",{"key":26,"text":27,"correct":18},"E","质量缺陷备案表由缺陷单位组织填写","ACD","2020版教材P210 \u002F 2019版教材P213 4.质量缺陷处理：根据水建管理（【2001】74号），水利工程实行施工质量缺陷备案及检查处理制度，故A正确；质量缺陷备案表由监理单位组织填写，故B、E错误；参见单位（人员）必须在质量缺陷备案表上签字，故C正确；质量缺陷备案资料必须按竣工验收的标准制备，故D正确；",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]