[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151774":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151774,803,2,"多选题","设计单位在施工过程中要（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","随时掌握施工现场情况",true,{"key":16,"text":17,"correct":14},"B","优化设计",{"key":19,"text":20,"correct":21},"C","审查施工组织设计",false,{"key":23,"text":24,"correct":14},"D","解决有关设计问题",{"key":26,"text":27,"correct":21},"E","审查工程变更","ABD","2020版教材P216 \u002F 2019版教材P219 设计单位的““在施工过程中要随时掌握施工现场情况，优化设计，解决有关设计问题””的一项主要工作。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]