[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151755":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151755,803,2,"多选题","根据《水利水电工程标准施工招标文件》，变更的范围包括（ ）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加或减少合同中永久工程项目的工程量，但未超过专用合同条款约定的百分比",false,{"key":16,"text":17,"correct":18},"B","改变合同中任何一项工作的质量或其他特性",true,{"key":20,"text":21,"correct":18},"C","改变合同工程的基线、标高、位置或尺寸",{"key":23,"text":24,"correct":18},"D","改变合同中任何一项工作的施工时间",{"key":26,"text":27,"correct":18},"E","改变已批准的施工顺序","BCDE","2020版教材P199 \u002F 2019版教材P202 在履行合同中发生以下情形之一，应进行变更：（1）取消合同中任何一项工作，但被取消的工作不能转由发包人或其他人实施。（2）改变合同中任何一项工作的质量或其他特性。（3）改变合同工程的基线、标高、位置或尺寸。（4）改变合同中任何一项工作的施工时间或改变巳批准的施工工艺或顺序。（5）为完成工程需要追加的额外工作。（6）增加或减少专用合同条款中约定的关键项目工程量超过其工程总量的一定数量百分比。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]