[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151724":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151724,803,2,"多选题","在合同实施过程中，项目法人可向承包人推荐分包人的条件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","由于承包人原因，导致某分部工程施工质量不满足合同要求",false,{"key":16,"text":17,"correct":18},"B","由于承包人原因导致工期拖延，承包人无力在合同规定期限内完成合同任务",true,{"key":20,"text":21,"correct":14},"C","由于重大设计变更导致施工方案重大变化，承包人要求增加投资的",{"key":23,"text":24,"correct":18},"D","由于重大设计变更导致施工方案重大变化，致使承包人不具备相应施工能力",{"key":26,"text":27,"correct":18},"E","项目有特殊技术要求、特殊工艺或涉及专利权保护的","BDE","2020版教材P173 \u002F 2019版教材P175 （5）在合同实施过程中，有下列情况之一的，项目法人可向承包人推荐分包人：①兩于重大设计变更导致施工方案重大变化，致使承包人不具备相应的施工能力。②由于承包人原因，导致施工工期拖延，承包人无力在合同规定的期限内完成合同任务。③项目有特殊技术要求、特殊工艺或涉及专利权保护的。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]