[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151709":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151709,803,2,"多选题","稽察工作机构可对设计单位提出的处理处罚建议包括（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","责令暂停施工",false,{"key":16,"text":17,"correct":18},"B","追究有关责任人的责任",true,{"key":20,"text":21,"correct":14},"C","清退出施工现场",{"key":23,"text":24,"correct":18},"D","不良行为记入水利建设市场主体信用档案",{"key":26,"text":27,"correct":14},"E","罚款","BD","2020版教材P168 \u002F 2019版教材P170 对“严重违反建设管理有关法律法规的项目管理和勘察（测）设计、施工、建设监理等参建单位，稽察工作机构可向有关部门单位提出以下处理处罚建议：（1）责令暂停施工。（2）追究有关责任人的责任。（3）将严重违规的施工、监理单位清退出施工现场。（4）将不良行为记人水利建设市场主体信用档案。（5）降低有关单位的资质等级或吊销其资质证书。（6）有关法律法规规定可以给予的其他处理处罚措施。 设计单位没有施工资质，所以A不能选择",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]