[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151690":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151690,803,2,"多选题","下列设计变更中，属于水利工程施工组织设计重大设计变更的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","主要料场场地变化",true,{"key":16,"text":17,"correct":18},"B","主要渣场场地变化",false,{"key":20,"text":21,"correct":14},"C","施工导流方式、导流建筑物方案变化",{"key":23,"text":24,"correct":14},"D","主要建筑物施工方案变化",{"key":26,"text":27,"correct":18},"E","主要建筑物施工进度变化","ACD","2020版教材P151 \u002F 2019版教材P153 以下施工组织设计变化而引起的工程设计变更为重大设计变更。①主要料场场地的变化。②水利枢纽工程的施工导流方式、导流建筑物方案的变化。③主要建筑物施工方案和工程总进度的变化。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]