[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151688":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151688,803,2,"多选题","建设项目在主体工程开工之前，必须具备的条件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目法人或建设单位已经设立",true,{"key":16,"text":17,"correct":18},"B","可行性研究报告已批准",false,{"key":20,"text":21,"correct":14},"C","建设资金已经落实",{"key":23,"text":24,"correct":14},"D","质量安全监督单位已经确定",{"key":26,"text":27,"correct":14},"E","主体工程施工单位和监理单位已经确定，并分别订立合同","ACDE","2020版教材P149 \u002F 2019版教材P151 建设实施阶段的工作内容中主体工程开工，必须具备以下条件：（1）项目法人或者建设单位巳经设立。（2）初步设计已经批准，施工详图设计满足主体工程施工需要。（3）建设资金已经落实。（4）主体工程施工单位和监理单位已经确定，并分別订立合同。（5）质量安全监督单位已经确定，并办理了质量安全监督手续。（6）主要设备和材料已经落实来源。（7）施工准备和征地移民等工作满足主体工程开工需要。选项B为开展施工准备的条件之一。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]