[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151683":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151683,803,2,"多选题","工程建设程序生产准备阶段的工作内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","生产组织准备",true,{"key":16,"text":17,"correct":14},"B","招收和培训人员",{"key":19,"text":20,"correct":21},"C","招标设计",false,{"key":23,"text":24,"correct":14},"D","生产物资准备",{"key":26,"text":27,"correct":14},"E","正常的生活福利设施准备","ABDE","2020版教材P147 \u002F 2019版教材P149 水利工程建设程序生产准备（运行准备）阶段。生产准备（运行准备）一般包括以下主要工作内容：（1）生产（运行）组织准备；（2）招收和培训人员；（3）生产（运行）技术准备；（4）生产（运行）物资准备；（5）正常的生活福利设施准备。选项C属于施工准备阶段。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]