[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151681":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151681,803,2,"多选题","在初步设计阶段，下列变动和修改需按程序上报原批准机关复审同意的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","非重大设计变更",false,{"key":16,"text":17,"correct":14},"B","生产性子项目之间的调整",{"key":19,"text":20,"correct":21},"C","建设标准调整",true,{"key":23,"text":24,"correct":21},"D","子项目调整",{"key":26,"text":27,"correct":21},"E","概算调整","CDE","2020版教材P147 \u002F 2019版教材P149 水利工程建设程序初步设计阶段的内容。在主要内容上有重要变动或修改（包括工程项目设计变更、子项目调整、建设标准调整、概算调整）等，应按程序上报原批准机关复审同意。选项AB在工程项目建设标准和概算投资范围内，依据批准的初步设计原则，一般非重大设计变更、生产性子项目之间的调整，由主管部门批准。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]