[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151679":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151679,803,2,"多选题","可行性研究报告重点解决项目建设的（ ）等问题。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术可行性",true,{"key":16,"text":17,"correct":18},"B","必要性",false,{"key":20,"text":21,"correct":14},"C","经济可行性",{"key":23,"text":24,"correct":14},"D","环境可行性",{"key":26,"text":27,"correct":14},"E","社会可行性","ACDE","2020版教材P146 \u002F 2019版教材P148 水利工程建设程序中的可行性研究报告阶段。根据批准的项目建议书，可行性研究报告应对项目进行方案比较，对技术上是否可行和经济上是否合理、环境以及社会影响是否可控进行充分的科学分析和论证，解决项目建设技术、经济、环境、社会可行性问题。经过批准的可行性研究报告，是项目决策和进行初步设计的依据。选项B为项目建议书阶段。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]