[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151669":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151669,803,2,"多选题","下列固结灌浆施工分序的原则中，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","应按分序加密的原则进行",true,{"key":16,"text":17,"correct":14},"B","同一区段内，周边孔应先行施工",{"key":19,"text":20,"correct":21},"C","同一坝块内，中间孔应先行施工",false,{"key":23,"text":24,"correct":14},"D","同一排孔孔与孔之间，可分为二序施工",{"key":26,"text":27,"correct":14},"E","可只分排序不分孔序","ABDE","2020\u002F2019教材P67 固结灌浆应按分序加密的原则进行。同一区段或同一坝块内，周边孔应先行施工。其余部位灌浆孔排与排之间和同一排孔孔与孔之间，可分为二序施工，也可只分排序不分孔序或只分孔序不分排序。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]