[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151667":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151667,803,2,"多选题","帷幕灌浆段注入量大而难以结束时，应首先结合地勘或先导孔资料查明原因，根据具体情况，可选用的处理措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","结束灌浆",false,{"key":16,"text":17,"correct":18},"B","灌注混合浆液",true,{"key":20,"text":21,"correct":18},"C","灌注膏状浆液",{"key":23,"text":24,"correct":18},"D","灌注速凝浆液",{"key":26,"text":27,"correct":18},"E","低压，浓浆，限流，限量，间歇灌浆","BCDE","2020\u002F2019教材P66 灌浆段注入量大而难以结束时，应首先结合地勘或先导孔资料查明原因，根据具伸:情况，可选用下列措施处理：（1）低压，浓浆，限流；限量，间歇灌浆。（2）灌注速凝浆液。（3）灌注混合浓液或膏状浆液。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]