[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151621":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151621,803,2,"多选题","吹填工程量按吹填土方量计算时，总工程量应为（ ）之和。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设计吹填方量",true,{"key":16,"text":17,"correct":14},"B","设计允许超填方量",{"key":19,"text":20,"correct":14},"C","地基沉降量",{"key":22,"text":23,"correct":24},"D","土方流失量",false,{"key":26,"text":27,"correct":24},"E","计算超深工程量","ABC","2020版教材P121 \u002F 2019版教材P123 吹填工程量按吹填土方量计算时，总工程量应为设计吹填方量与设计允许超填方量以及地基沉降量之和，超填厚度不应大于0.2 m,吹填士流失量也应计算并列出；按取土量计算工程量时，吹填工程量应疏浚工程的规定执行。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]