[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151620":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151620,803,2,"多选题","疏浚工程中局部欠挖出现（ ）情况时，应进行返工处理。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","欠挖厚度大于设计水深的5%，且大于30cm",true,{"key":16,"text":17,"correct":18},"B","欠挖厚度小于设计水深的3%",false,{"key":20,"text":21,"correct":14},"C","横向浅埂长度大于设计底宽的5%，且大于2m",{"key":23,"text":24,"correct":14},"D","纵向浅埂长度大于2.5m",{"key":26,"text":27,"correct":14},"E","一处超挖面积大于5.0m2","ACDE","2020版教材P121 \u002F 2019版教材P123 （5）局部欠挖如超出下列规定时，应进行返工处理：①欠挖厚度小于设计水深的5%,且大于0.3m。②横向浅埂长度小于设计底宽的5%，且大于2.0m。③纵向浅埂长度小于2.5m。④一处超挖面积不大于5.0m2。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]