[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151613":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151613,803,2,"多选题","堤防填筑作业面要求是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分层统一铺土，统一碾压",true,{"key":16,"text":17,"correct":18},"B","分层分片铺土，统一碾压",false,{"key":20,"text":21,"correct":18},"C","分层统一铺土，分片碾压",{"key":23,"text":24,"correct":14},"D","上下层分段接缝错开",{"key":26,"text":27,"correct":18},"E","以上答案都不对","AD","2020版教材P117 \u002F 2019版教材P119 二、填筑作业面的要求：（3）作业面应分层统一铺土、统一碾压，严禁出现界沟，上、下层的分段接缝应错开。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]