[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151612":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151612,803,2,"多选题","下列关于堤身填筑的技术要求，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","水平分层，不得顺坡铺填",true,{"key":16,"text":17,"correct":18},"B","机械施工时分段作业面长度不应小于200m，人工施工时段长可适当减短",false,{"key":20,"text":21,"correct":14},"C","已铺土料表面在压实前被晒干时，应洒水润湿",{"key":23,"text":24,"correct":14},"D","光面碾压的黏性土填料层，在新层铺料前，应作刨毛处理",{"key":26,"text":27,"correct":14},"E","作业面应分层统一铺土，统一碾压，上、下层的分段接缝应错开","ACDE","2020版教材P117 \u002F 2019版教材P119 二、填筑作业面的要求：（1）地面起伏不平时，应按水平彡层由低处开始逐层填筑，不得顺坡铺填； （2）分段作业面长度，机械施工时段长不应小于100m，人工施工时段长可适当减短。 （3）作业面应分层统一铺土、统一碾压，严禁出现界沟，上、下层的分段接缝应错开。 （6）已铺土料表面在压实前被晒干时，应采用铲除或洒水湿润等方法进行处理。 （7）用光面碾磙压实黏性土填筑层，在新层铺料前，应对压光层面作刨毛处理。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]