[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151611":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151611,803,2,"多选题","堤基清理的要求包括（ ）等。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","堤基清理范围包括堤身、铺盖和压载的基面",true,{"key":16,"text":17,"correct":14},"B","应将堤基范围内的淤泥、腐殖土、不合格土及杂草、树根等清除干净",{"key":19,"text":20,"correct":21},"C","堤基内的井窖、树坑、坑塘等应按高于堤身的要求进行分层回填处理",false,{"key":23,"text":24,"correct":14},"D","堤基清埋后，应在第一层铺填前进行平整压实",{"key":26,"text":27,"correct":21},"E","堤基清理边线应比没计基面边线宽出50～80cm","ABD","2020版教材P116 \u002F 2019版教材P118 一、堤基清理的要求：（1）堤基清理范围包括堤身、铺盖和压载的基面。堤基清理边线应比设计基面边线宽出30-50cm。老堤加高培厚，其清理范围包括堤顶和堤坡。（3）堤基清理时，应将堤基范围内的淤泥、腐殖土、泥炭、不合格土及杂草、树根等清除干净。（4）堤基内的井窖、树坑、坑塘等应按堤身要求进行分层回填处理。（5）堤基清理后’应在第一层铺填前进行平整压实，压实后土体干密度应符合设计要求。（6）堤基冻结后有明显冰夹层、冻胀现象时未经处理，不得在其上施工。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]