[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151588":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151588,803,2,"多选题","下列关于施工缝的处理，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","新混凝土浇筑前，应用高压水枪或风砂枪将老混凝土表面含游离石灰的水泥膜清除",true,{"key":16,"text":17,"correct":18},"B","纵缝表面必须凿毛，且应冲洗干净",false,{"key":20,"text":21,"correct":14},"C","采用高压水冲毛，视气温高低，可在浇筑后5～20h进行",{"key":23,"text":24,"correct":14},"D","用风砂枪冲毛时，一般应在浇后一两天进行",{"key":26,"text":27,"correct":14},"E","施工缝面凿毛或冲毛后，应用压力水冲洗干净","ACDE","2020版教材P96 \u002F 2019版教材P98 2.施工缝处理 施工缝指浇筑块间临时的水平和垂直结合缝，也是新老混凝土的结合面。在新混凝土浇筑前，应当采用适当的方法（高压水枪、风沙枪、风镐、钢刷机、人工凿毛等）将老混凝土表面含游离石灰的水泥膜（乳皮）清除，并使表层石子半露，形成有利于层间结合的麻面。对纵缝表面可不凿毛，但应冲洗干净，以利灌浆。采用高压水冲毛，视气温高低，可在浇筑后5-20h进行；当用风砂枪冲毛时，一般应在浇后一两天进行。施工缝面凿毛或冲毛后，应用压力水冲洗干净，使其表面无渣、无尘，才能浇筑混凝土。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]