[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151579":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151579,803,2,"多选题","堆石坝施工中，砂砾料压实检查项目包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","干密度",true,{"key":16,"text":17,"correct":18},"B","孔隙率",false,{"key":20,"text":21,"correct":18},"C","含水量",{"key":23,"text":24,"correct":14},"D","相对密度",{"key":26,"text":27,"correct":14},"E","颗粒级配","ADE","2020版教材P89 \u002F 2019版教材P92 （3）坝料压实检查项目、取样次数见表IF415022。其中砂砾料检查项目有颗粒级配、干密度和相对密度；渗透系数按设计要求进行检测。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]