[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151568":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151568,803,2,"多选题","下列关于土石坝填筑接头处理的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","层与层之间分段接头应错开一定距离",true,{"key":16,"text":17,"correct":18},"B","分段条带应与坝轴线垂直布置",false,{"key":20,"text":21,"correct":14},"C","黏土心墙宜采用土、砂料平起填筑",{"key":23,"text":24,"correct":18},"D","接坡坡比宜陡于1:3",{"key":26,"text":27,"correct":14},"E","靠近建筑物部位宜采用小型机械或人工夯实","ACE","2020版教材P85 \u002F 2019版教材P88 六、接头处理（1）在坝体填筑中，层与层之间分段接头应错开一定距离，同时分段条带应与坝轴线平行布置，各分段之间不应形成过大的高差。接坡坡比一般缓于1:3。（2）坝体填筑中，为了保护黏土心墙或黏土斜墙不致长时间暴露在大气中遺受影响，一般都采用土、砂平起的施工方法。土、砂平起填筑，采用两种施工方法：一种是先土后砂法，即先填土料后填砂砾反滤料;另一种是先砂后土法，即先填砂砾反滤料后填土料。（3）对于坝身与混凝土结构物（如涵管、刺墙等）的连接，靠近混凝土结构物部位不能采用大型机械压实时，可采用小型机械夯或人工夯实。填土碾压时，要注意混凝土结构物两侧均衡填料压实，以免对其产生过大的侧向压力，影响其安全。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]