[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151552":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151552,803,2,"多选题","水利水电地下工程施工方式包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","全面开挖方式",false,{"key":16,"text":17,"correct":18},"B","全断面开挖方式",true,{"key":20,"text":21,"correct":18},"C","先导洞后扩大开挖方式",{"key":23,"text":24,"correct":18},"D","台阶扩大开挖方式",{"key":26,"text":27,"correct":18},"E","分部分块开挖方式","BCDE","2020\u002F2019版教材P81 根据地下洞室断面分类，结合施工机械和技术水平情况，地下工程可采取全断面开挖、先导洞后扩大开挖、台阶扩大开挖、分部分块开挖等方式进行施工。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]