[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151544":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151544,803,2,"多选题","基坑经常性排水，排水总量应包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","排水时降水量",true,{"key":16,"text":17,"correct":14},"B","覆盖层中的含水量",{"key":19,"text":20,"correct":14},"C","施工弃水量",{"key":22,"text":23,"correct":14},"D","围堰和基础在设计水头的渗流量",{"key":25,"text":26,"correct":27},"E","堰身中的含水量",false,"ABCD","2020\u002F2019教材P58 经常性排水应分别计算围堰和地基在设计水头的渗流量、覆盖层中的含水量、排水时降水量及施工弃水量。其中降水量按抽水时段最大日降水量在当天抽干计算; 施工弃水量与降水量不应叠加。基坑渗水量可分析围堰形式、防渗方式、瑕基情况、地质资料可靠程度、渗流水头等因素适当扩大。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]