[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151535":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151535,803,2,"多选题","通过建筑物导流的主要方式包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","混凝土坝体中的底孔导流",true,{"key":16,"text":17,"correct":18},"B","涵管导流",false,{"key":20,"text":21,"correct":14},"C","混凝土坝体上预留缺口导流",{"key":23,"text":24,"correct":18},"D","隧洞导流",{"key":26,"text":27,"correct":14},"E","混凝土坝体上梳齿孔导流","ACE","2020\u002F2019教材P50 通过建筑物导流的主要方式，包括设置在混凝土坝体中的底孔导流、混凝土坝体上预留缺口导流、梳齿孔导流，平原河道上低水头河床式径流电站可采用厂房导流等。这种导流方式多用于分期导流的后期阶段。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]