[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151508":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151508,803,2,"多选题","地震荷载是大坝遭受地震时所承受的荷载，包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","地震惯性力",true,{"key":16,"text":17,"correct":14},"B","水平向地震动水压力",{"key":19,"text":20,"correct":21},"C","水平向地震静水压力",false,{"key":23,"text":24,"correct":14},"D","水平向地震动土压力",{"key":26,"text":27,"correct":21},"E","水平向地震静土压力","ABD","2020\u002F2019教材P30 水工建筑物抗震设计。地震荷载是大坝遭受地震时所承受的荷载，包括地震惯性力、水平向地震动水压力和地震动土压力等.",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]