[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151497":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151497,803,2,"多选题","永久性水工建筑物的洪水标准，应根据建筑物的()确定。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投资",false,{"key":16,"text":17,"correct":14},"B","规模",{"key":19,"text":20,"correct":21},"C","结构类型",true,{"key":23,"text":24,"correct":21},"D","级别",{"key":26,"text":27,"correct":14},"E","建设工期","CD","2020\u002F2019教材P16 水利水电工程永久性水工建筑物的洪水标准,课本没有对此作出描述，但通过课本的表格信息。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]