[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151474":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151474,803,2,"多选题","疏浚工程中没有包含在《工程量清单》疏浚工程相应项目有效工程量的每立方米单价中，需要另行计量支付的工作内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计断面以外的超挖量",false,{"key":16,"text":17,"correct":14},"B","施工期自然回淤量",{"key":19,"text":20,"correct":21},"C","排泥区围堰",true,{"key":23,"text":24,"correct":21},"D","浚前扫床",{"key":26,"text":27,"correct":14},"E","使用辅助船只","CD","疏浚工程的辅助措施(如浚前扫床和障碍物的清除、排泥区围堰、隔埂、退水口及排水渠等项目)，另行计量支付。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]