[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151471":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151471,803,2,"多选题","下列施工用电属于三类负荷的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","混凝土预制构件厂",false,{"key":16,"text":17,"correct":18},"B","钢筋加工厂",true,{"key":20,"text":21,"correct":14},"C","隧洞开挖",{"key":23,"text":24,"correct":18},"D","木材加工厂",{"key":26,"text":27,"correct":14},"E","混凝土拌合系统","BD","C：一类负荷；A、E：二类负荷。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]